HcoRealEstates
Sobha International City Phase 3 Gurgaon

Sobha International City Phase 3 Gurgaon

Last Update : Apr 11, 2023
Price
4.93 Cr. Approx
Sizes
267 Sq. Yards
Offered Payment Plan
CLP
Project Status
Ready to Move

Sobha International City Phase 3 Price List

Price List

Plot Area 270 Sq. Yards
Saleable Built-up Area (SBA) 4122 Sq. Ft.
Basic Sale Price (BSP) Rs. 4.93 Crores
EDC (4285/- Per Sq. Yards of Plot Area) Rs. 11.53 Lacs
IDC (708/- Per Sq. Yards of Plot Area) Rs. 1.91 Lacs
Maintenance Deposit (200 Per Sq. Ft. of SBA) Rs. 8.24 Lacs
Club Membership Rs. 2.00 Lacs
Preferential Location Charges (PLC) (on BSP) Green facing / Adjoining - 5%, Corner - 5%

Payment Plan

Booking amount Rs. 25 Lacs
30 days from booking 25% (less booking amount paid)
60 days from booking 100% EDC / IDC
On completion of foundation work or 1st June 2015, whichever is later 10%
On completion of basement roof slab or 90 days from the PRL date of completion of foundation work, whichever is later 10%
On completion of ground floor roof slab or 90 days from the PRL date of completion of basement roof slab, whichever is later 10%
On completion of first floor roof slab or 90 days from the PRL date of completion of ground floor roof slab, whichever is later 10%
On completion of second floor roof slab or 90 days from the PRL date of completion of first floor roof slab, whichever is later 10%
On completion of block work excluding shafts, ducts etc. 10%
On completion of internal plastering excluding shafts, ducts 5%
On completion of internal flooring 5%
On handover / offer of handover 5%
  • The pricing for individual units might vary based on the size of the plot.
  • The Saleable Built-up Area (SBA) is subject to minor changes based on approvals from govt. authorities.
  • External Development Charges (EDC) and Infrastructure Development Charges (IDC) are pro - rated per unit as applicable to this project. In case of any upward revision in future by the govt. agencies, the same would be charged on pro-rata basis from the customer.
  • Maintenance Deposit and Club Membership fee are payable at the time of handover.
  • Government charges towards electricity, water & sanitary are to be ascertained and payable by the customers at the time of possession and are not included in the above cost.
  • Service Tax, VAT and other government levies or duties as applicable at present or to be applicable in future shall be extra and will be borne by the customer and are not included in the above cost.
  • Registration and Stamp duty charges to be ascertained and payable by the customer at the time of possession and are not included in the above cost.
  • Any other statutory charges which may be imposed by the authorities from time to time will also be payable by the customers at actuals
  • Each payment shall become payable on demand irrespective of serial number in which they are listed above.